SHORT RANGE EXAMPLE CONSTRUCTION 2022
- Mountain Industrial Boulevard at Tuckerstone Parkway
- Install eyebrow/loon to all U-turns for WB-60 trucks on Mountain Industrial Boulevard
- Install raised barrier island to prohibit southbound left turns onto Mountain Industrial Boulevard
- E Ponce de Leon Avenue at Rock Mountain Boulevard
- Install pedestrian crosswalk and signal on E Ponce de Leon Avenue
- Install pedestrian landing area and sidewalk at MARTA bus stop on E Ponce de Leon Avenue
- Flashing yellow signal for left turns from eastbound E Ponce de Leon Avenue
- Install supplemental “Signal Ahead” signage on Rock Mountain Boulevard
- Install sidewalks along Rock Mountain Boulevard
- Increase turning radii and relocate utility poles at the NW and NE corners of Rock Mountain Boulevard
SHORT RANGE EXAMPLE CONSTRUCTION 2023/2024
SR 236 (Hugh Howell Road at Mtn. Ind. Blvd
On schedule for construction to commence in late 2023 or early 2024. The project will include dual left turn lanes north and southbound on MIB at Hugh Howell and a right turn lane on Hugh Howell eastbound at MIB.LONG RANGE EXAMPLE – CONST 2025/2026
HWY 78 INTERCHANGE AND MOUNTAIN INDUSTRIAL BLVD
Relocate the off ramps on Hwy 78 at Mountain Industrial Boulevard (MIB) farther from the bridge to improve sight visibility. This will include a a narrow median on MIB from Elmdale to Greer Circle,including improvements to signal timing and intersection radius improvements. The narrow median from Greer to Elmdale will dramatically decrease the number of accidents on MIB – which has the highest accident history on this section of roadway in the City of Tucker. Construction is anticipated to commence in 2025. PROJECT LIMITS: GREER TO ELMDALE
Location: TSCID District
Details: The TSCID is under contract with Wi-Skies to begin photometric design of various streets throughout the CID. In partnership with Georgia Power, the City of Tucker and DeKalb County, the CID will be developing lighting layouts on all CID streets over the next 12-15 months. These layouts will include cost estimates for new or upgraded light fixtures and new poles where the photometric design work indicates lighting is necessary. The CID will be reaching out to owners on each street to discuss the project details, cost sharing options and schedule for implementation.